Good afternoon Mr. Brendel

As a follow-up from our discussions and information provided by the Project Engineer of Record (original landscape plans), below are questions that were forwarded to us by Mr. Eric Carpenter from his attendance at the Venetian Islands HOA meeting held last week:

  1. When will Rivo Alto be done (first lift)?

Lanzo is scheduled to be completed by this Friday, March 4, 2016.

  1. When will the lights be on (full neighborhood – broken down by island):

San Marino Island by end of March, Dilido by Mid-April and Rivo Alto by end of April.

  1. Are the old lights coming down?  When?

Once the lights are energize and accepted, FPL will coordinate with the City and schedule the removal.

  1. When will final lift be complete?

Late 2016.

  1. Landscaping:

The amount of canopy area to be replaced by the permit is 64,456 sq. ft. –  we are looking for direction from Commission on the handling of encroachments

Mr. Brendel, as always we are available to answer any additional questions, just call

Thanks

Mark

MARK E. TOMCZYK, P.E., SR. CAPITAL PROJECTS COORDINATOR

Office of Capital Improvement Projects 
1700 Convention Center Drive, Miami Beach, FL 33139
 Tel:  305.673.7071

Fax: 305.673.7073

www.miamibeachfl.gov